Replacement
Client: Enbridge
Project Value: $5,200,000
Project Schedule: July – October 2022
Enbridge identified integrity issues on the NS 30” Mainline at Falls Lake Crossing, between KP 43.1 and 43.5.
The project scope included:
- Replacement of 120m of 30” NPS pipe through Falls Lake Creek and a 60m replacement of a geohazard.
- 24hr water pumping using the dam and pump method.
- Large cuts and earthworks required for tie-ins. This work was outage driven, within proximity to other in-service facilities and was within a busy Provincial Park with limited TWP.