Pipeline Replacement
Client: Enbridge
Project Value: $3,537,000.00
Project Schedule: May – October 2025
The project scope included:
- Replaced the NPS 30 valve assembly, receiver and NPS 10 blowdown piping assembly at the KP 90.6 Compressor Station 5 (CS5), KP 30.1 Dunkley crossover valve, and the KP19.7 crossover.
- NPS 30 valve and associated piping installed, along with the replacement of the NPS 10 riser, NPS 10 blowdown spools and NPS 12 crossover spools.
- The new assembly supported by the installation of two structural steel supports and new concrete foundations.